Project Duration
Stipulated Date of Commencement
February 07 2014
Stipulated Date of Completion /
Likely Date of Completion March 06 2014
Likely Date of Completion March 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,880,499.00
Awarded for
₹ 2,771,319.00
Contractors
M/s. Technoworld,
Consultants
In-house (GSIDC)