Project Duration
Stipulated Date of Commencement
October 27 2014
Stipulated Date of Completion /
Likely Date of Completion November 26 2014
Likely Date of Completion November 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,569,033.00
Awarded for
₹ 1,722,777.57
Project highlights
Providing of additional loose Interior, signages etc.
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.