Project Duration
Stipulated Date of Completion /
Likely Date of Completion November 23 2009
Likely Date of Completion November 23 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,079,636.00
Awarded for
₹ 1,017,000.00
Project highlights
4 nos. LCD Televisions with Headphones, Public Address System (Amplifier, Mixer, Speakers, Table Mike, Cordless Mike, Mike with Stand, Collar Mike, Rack), CCTV Surveillance Cameras, Digital Video Recorders, LCD Monitors, U Racks, Projection Screen with Tripod and Voltage Stabilizers for Televisions and Digital Photocopiers
Contractors
M/s. Reconnoitre Systems
Consultants
In-house (GSIDC)