Project Duration
Stipulated Date of Commencement
November 26 2009
Stipulated Date of Completion /
Likely Date of Completion December 05 2009
Likely Date of Completion December 05 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,903.00
Awarded for
₹ 23,125.00
Contractors
M/s. Intersales
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.
View Project
RFID System.
View Project
Additional electrical work.
View Project





