Project Duration
Stipulated Date of Commencement
April 30 2011
Stipulated Date of Completion /
Likely Date of Completion June 15 2011
Likely Date of Completion June 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,655,070.00
Awarded for
₹ 6,793,290.00
Project highlights
Providing chairs and sofas at various locations in the library
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.