Project Duration
Stipulated Date of Commencement
November 19 2010
Stipulated Date of Completion /
Likely Date of Completion December 30 2010
Likely Date of Completion December 30 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ -
Awarded for
₹ 6,94,890.00
Contractors
M/s. Technical Drying Services (Asia) Pvt. Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.