Project Duration
Stipulated Date of Commencement
November 19 2010
Stipulated Date of Completion /
Likely Date of Completion December 30 2010
Likely Date of Completion December 30 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ -
Awarded for
₹ 99,55,323.00
Contractors
M/s. Bry Air (Asia) Pvt. Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
See Similar Projects
Restoration and facilities Upgradation of the existing Kala Academy, Panaji, Goa.
View Project
Landscaping work
View Project
Development & Beautification of open spaces into Gardens at Nina Pinto Colony, Caculo Colony & Albamar Colony in Ward No.9 and 10 of Corporation of the City of Panaji.
View Project