Project Duration
Stipulated Date of Commencement
January 27 2013
Stipulated Date of Completion /
Likely Date of Completion April 26 2013
Likely Date of Completion April 26 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 33,774,924.00
Awarded for
₹ 27,041,231.40
Project highlights
Audio- Video work for the project
Contractors
M/s. AGC Networks Limited
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.