Project Duration
Stipulated Date of Commencement
February 17 2013
Stipulated Date of Completion /
Likely Date of Completion May 16 2013
Likely Date of Completion May 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,378,922.00
Awarded for
₹ 9,380,500.00
Project highlights
Stage craft work for the project
Contractors
M/s. Pandurang Kothare
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Development & Beautification of open spaces into Gardens at Nina Pinto Colony, Caculo Colony & Albamar Colony in Ward No.9 and 10 of Corporation of the City of Panaji.
View Project
Demolition and reconstruction of Market Complex at Bhoma Adcolna Panchayat Banastarim Goa -Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works
View Project
Renovation of Rajiv Gandhi Kala Mandir at Ponda.
View Project