Project Duration
Stipulated Date of Commencement
February 11 2010
Stipulated Date of Completion /
Likely Date of Completion July 10 2010
Likely Date of Completion July 10 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,877,563.00
Awarded for
₹ 9,939,420.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Construction of Panchayat Ghar at Village Panchayat Veiling –Priol- Cuncoliem
View Project
Re-Construction of Panchayat building and Community Center at Neturlim in Sanguem Taluka. V.P. Neturlim.
View Project
External Lighting Works
View Project





