Project Duration
Stipulated Date of Commencement December 25 2010
Stipulated Date of Completion /
Likely Date of Completion
May 24 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 55,35,000.00
Awarded for ₹ 6,420,000.00
 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 