Project Duration
Stipulated Date of Commencement
October 10 2014
Stipulated Date of Completion /
Likely Date of Completion December 10 2014
Likely Date of Completion December 10 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 30,184,064.00
Awarded for
₹ 27,461,337.00
Project highlights
The scope of work invloves supply of decorative street light poles near Se Cathedral Church, Basilica of Bom Jesus and Mont Boa Vista at Old Goa
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. LKS India Pvt. Ltd.