Project Duration
Stipulated Date of Commencement November 12 2014
Stipulated Date of Completion /
Likely Date of Completion
December 11 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,646,556.00
Awarded for ₹ 5,448,198.15

Project highlights

Construction of Footpath at Old Goa for Exposition 2014