Project Duration
Stipulated Date of Commencement
November 12 2014
Stipulated Date of Completion /
Likely Date of Completion January 11 2015
Likely Date of Completion January 11 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,681,148.00
Awarded for
₹ 16,543,756.55
Project highlights
Construction of Washrooms at Old Goa for Exposition 2014
Contractors
M/s. R.S. Lawande
Consultants
M/s. LKS India Pvt. Ltd.