Project Duration
Stipulated Date of Commencement
October 17 2014
Stipulated Date of Completion /
Likely Date of Completion December 16 2014
Likely Date of Completion December 16 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,681,148.00
Awarded for
₹ 16,754,331.00
Project highlights
Construction of toilet blocks near Basilica and prking area for Exposition 2014.
Contractors
M/s. Abhiyant Infratech LLP
Consultants
M/s LKS India Pvt. Ltd.