Project Duration
Stipulated Date of Commencement
July 14 2004
Stipulated Date of Completion /
Likely Date of Completion October 31 2004
Likely Date of Completion October 31 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 227,419,000.00
Awarded for
₹ 241,764,000.00
Project highlights
Repairs and restoration works, air conditioning, furniture / interior work, road work and plumbing plus electrical work.
Contractors
M/s. Unity Infraprojects Ltd.
Consultants
M/s. UCJ Architecture & Environment