Project Duration
Stipulated Date of Commencement November 07 2017
Stipulated Date of Completion /
Likely Date of Completion
November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 827,427.00
Awarded for ₹ 848,095.00

Project highlights

The scope of work includes replacement of non-functional CFL light fixtures with the LED light fixtures, LED street light fixtures, repairs of street lights in the courtyard of ESG premises.

 
Gallery Image
Contractors
M/S. Volton Engineering India Pvt Ltd
Gallery Image
Consultants
M/S.Vaishali Pednekar Associates
 
Similar Projects

See Similar Projects

Similar Project

External Electrical works.

View Project
Similar Project

Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations.

View Project
Similar Project

Construction of Toilet Block at Chapora

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.