Project Duration
Stipulated Date of Commencement October 01 2013
Stipulated Date of Completion /
Likely Date of Completion
October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,326,816.00
Awarded for ₹ 10,499,999.00

Project highlights

The scope of work involves dismantling of the existing nonfunctional VRV System and installation of the new VRV Air-Conditioning System at Maquinez Palace and Maquinez Palace Annex Building.