Project Duration
Stipulated Date of Commencement
September 28 2007
Stipulated Date of Completion /
Likely Date of Completion November 07 2007
Likely Date of Completion November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 730,340.00
Awarded for
₹ 730,340.00
Contractors
M/s. MRH Digital Systems Pvt. Ltd.
Consultants
M/s. Effective Architectural Services