Project Duration
Stipulated Date of Commencement
April 28 2007
Stipulated Date of Completion /
Likely Date of Completion October 27 2007
Likely Date of Completion October 27 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,781,679.10
Awarded for
₹ 37,000,000.05
Project highlights
The Restoration & refurbishment of FDA building and Maquinez palace was planned to house offices for Directorate of Film Festivals, Press Information Bureau, Media Centre, Offices of the Entertainment Society of Goa, Viewing rooms, Auditorium and associated infrastructure, Presentation room, Art Gallery, Film Museum, Print Unit and Storage, Guest Rooms, Associated functions of registration, conferences, briefing room, lounge, support facilities in toilets, services, etc.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Effective Architectural Services
Sub Works
This project involved 9 sub works. The details of the same available below
1
Interiors and Furniture work.
100% completed
Project Duration
Stipulated Date of Commencement
October 08 2007
Stipulated Date of Completion /
Likely Date of Completion November 07 2007
Likely Date of Completion November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,758,464.82
Awarded for
₹ 16,967,500.48
Contractors
M/s. Concept Creators
Consultants
M/s. Effective Architectural Services
2
EPABX system.
100% completed
Project Duration
Stipulated Date of Commencement
October 29 2007
Stipulated Date of Completion /
Likely Date of Completion November 12 2007
Likely Date of Completion November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 903,000.00
Awarded for
₹ 584,000.00
Contractors
M/s. Coral Telecom Ltd.
Consultants
M/s. Effective Architectural Services
3
Facilitation Services, Installation, Testing & Commissioning of Theatre equipments.
100% completed
Project Duration
Stipulated Date of Commencement
September 28 2007
Stipulated Date of Completion /
Likely Date of Completion November 07 2007
Likely Date of Completion November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 730,340.00
Awarded for
₹ 730,340.00
Contractors
M/s. MRH Digital Systems Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
4
Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
October 04 2007
Stipulated Date of Completion /
Likely Date of Completion October 31 2007
Likely Date of Completion October 31 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,930,239.00
Awarded for
₹ 28,515,999.00
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
5
Theatre System (non-proprietory).
100% completed
Project Duration
Stipulated Date of Commencement
October 04 2007
Stipulated Date of Completion /
Likely Date of Completion November 03 2007
Likely Date of Completion November 03 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,243,325.00
Awarded for
₹ 11,842,038.03
Contractors
M/s. MRH Digital Systems Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
6
Construction of RCC sump and pumping system.
100% completed
Project Duration
Stipulated Date of Commencement
October 16 2008
Stipulated Date of Completion /
Likely Date of Completion November 29 2008
Likely Date of Completion November 29 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,50,542.00
Awarded for
₹ 1,095,710.50
Contractors
M/s.P. Gangadharan
Consultants
M/s. Effective Architectural Services
7
HVAC works.
100% completed
Project Duration
Stipulated Date of Commencement
October 08 2007
Stipulated Date of Completion /
Likely Date of Completion November 07 2007
Likely Date of Completion November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,395,782.00
Awarded for
₹ 19,798,057.87
Contractors
M/s. ETA General Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
8
Fire Hydrant / Alarm System.
100% completed
Project Duration
Stipulated Date of Commencement
October 29 2007
Stipulated Date of Completion /
Likely Date of Completion November 12 2007
Likely Date of Completion November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,517,253.00
Awarded for
₹ 3,910,525.00
Contractors
M/s. Max Alert Systems Pvt. Ltd
Consultants
M/s. Effective Architectural Services
9
Additional miscellaneous works
100% completed
Project Duration
Stipulated Date of Commencement
June 09 2009
Stipulated Date of Completion /
Likely Date of Completion September 07 2009
Likely Date of Completion September 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,343,352.00
Awarded for
₹ 4,609,470.95
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Effective Architectural Services
See Similar Projects
Signages work
View Project
Internal, external and special lighting fixtures (Part B : External lights and façade lighting)
View Project
Deep Cleaning and Housekeeping Work
View Project