Project Duration
Stipulated Date of Commencement
November 21 2014
Stipulated Date of Completion /
Likely Date of Completion December 20 2014
Likely Date of Completion December 20 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,984,822.00
Awarded for
₹ 2,958,853.00
Project highlights
repairs and painting of Maquinez Palace for IFFI 2014.
Contractors
M/s. Michael & Michael Constructions
Consultants
M/s. UCJ Architecture & Environment