Project Duration
Stipulated Date of Commencement December 12 2012
Stipulated Date of Completion /
Likely Date of Completion
January 07 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,312,379.00
Awarded for ₹ 27,265,350.00

Project highlights

Widening of various roads by constructing retaining walls, providing full grout and hotmixing from Banyan tree to Pausada Hotel upto Fat Fish Restaurant, and from Fat Fish Restaurant to Baga Bridge in Calangute constituency. Approxitmate length of roads- 3.70 km

 
Gallery Image
Contractors
M/s.Ritesh Developers Pvt. Ltd
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Ancillary Works at Kala Academy Building Campal Panaji – Goa

View Project
Similar Project

Soft landscaping.

View Project
Similar Project

Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.