Project Duration
Stipulated Date of Commencement
March 07 2014
Stipulated Date of Completion /
Likely Date of Completion October 06 2014
Likely Date of Completion October 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,00,00,000.00
(Rate Contract)
Awarded for
₹ 30,000,000.00
Project highlights
Beautification work by providing pavers for footpaths and bencches, landscaping, repairs to drains with precast slab within Panjim municipal limits
Contractors
M/s.H Candolkar & Sons
Consultants
M/s.Nitin Arolkar