Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion June 30 2013
Likely Date of Completion June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,157,599.20
Contractors
M/s. Gaurish P. Naik
Consultants
In-house (GSIDC)