Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion June 30 2013
Likely Date of Completion June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,157,599.20
Contractors
M/s. Gaurish P. Naik
Consultants
In-house (GSIDC)
See Similar Projects
Renovation of Building of Directorate of Higher Education, Porvorim, Goa – Civil, Electrical, Lift, HVAC, Interior and Furniture work
View Project
Additional electrical and networking work.
View Project
Construction of High Court Complex at Penha de Franca, Porvorim.
View Project