Status
100%
Completed
Project highlights
Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations
Contractors
Consultants
Sub Works
This project involved 6 sub works. The details of the same available below
1
Panaji to Patradevi (Part I) – Chainage 0.00 km. to 21.90 km.
100% completed
Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion June 20 2013
Likely Date of Completion June 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 853,639.00
Awarded for
₹ 840,171.60
Contractors
M/s.Rakesh Kambli
Consultants
In-house (GSIDC)
2
Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.
100% completed
Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion June 20 2013
Likely Date of Completion June 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 853,639.00
Awarded for
₹ 840,171.60
Contractors
M/s.Rakesh Kambli
Consultants
In-house (GSIDC)
3
Panaji to Pollem (Part I) – Chainage 0.00 km. to 31.30 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion June 30 2013
Likely Date of Completion June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,280,289.25
Contractors
M/s.H. Candolcar & Sons
Consultants
In-house (GSIDC)
4
Panaji to Pollem (Part II) – Chainage 31.30 km. to 62.60 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion June 30 2013
Likely Date of Completion June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,157,599.20
Contractors
M/s. Gaurish P. Naik
Consultants
In-house (GSIDC)
5
Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 16 2013
Stipulated Date of Completion /
Likely Date of Completion July 16 2013
Likely Date of Completion July 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,123,044.00
Contractors
M/s. Veejay Facility Management Ltd.
Consultants
In-house (GSIDC)
6
Cortalim to Verna via Airport – 24.00 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 16 2013
Stipulated Date of Completion /
Likely Date of Completion July 16 2013
Likely Date of Completion July 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 935,546.00
Awarded for
₹ 880,992.00
Contractors
M/s. Veejay Facility Management Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Construction of Office Building for Directorate of Accounts at Porvorim, Goa
View Project