Project Duration
Stipulated Date of Commencement
January 10 2018
Stipulated Date of Completion /
Likely Date of Completion November 30 2018
Likely Date of Completion November 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 345,101.00
Awarded for
₹ 342,014.00
Project highlights
SITC of 2 Nos. 5.5TR ductable units for MRI section at Goa Medical College, Bambolim-Goa.
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
In-house (GSIDC)