Project Duration
Stipulated Date of Commencement
June 15 2006
Stipulated Date of Completion /
Likely Date of Completion January 14 2007
Likely Date of Completion January 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,834,633.00
Awarded for
₹ 42,696,401.00
Project highlights
Central air conditioning for Ward Block and other buildings at GMC, Bambolim.
Contractors
M/s. Voltas Limited
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Upgradation of Pay Ward at Goa Medical College, Bambolim, Goa – Additional furniture works
View Project
Supply, Installation, Testing and Commissioning of computer network with hardware and software.
View Project
Motruary Cabinet Works
View Project