Project Duration
Stipulated Date of Commencement
August 21 2020
Stipulated Date of Completion /
Likely Date of Completion August 20 2021
Likely Date of Completion August 20 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 588,124.00
Awarded for
₹ 588,124.00
Project highlights
Maintenance of lifts at GMC
Contractors
M/s. Schindler India Pvt. Ltd.,
Consultants
In-house (GSIDC)