Project Duration
Stipulated Date of Commencement July 05 2018
Stipulated Date of Completion /
Likely Date of Completion
July 04 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 287,000.00
Awarded for ₹ 287,000.00

Project highlights

Maintenance of UPS system at GMC

 
Gallery Image
Contractors
M/s. Vertiv Energy Pvt. Ltd.,
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

External electrical work

View Project
Similar Project

Supply Installation Testing & Commissioning of Bio Medical Equipment (Part II) Colour doppler & Ultra Sonography.

View Project
Similar Project

UPS works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.