Project Duration
Stipulated Date of Commencement July 23 2019
Stipulated Date of Completion /
Likely Date of Completion
November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 800,000.00
Awarded for ₹ 800,000.00

Project highlights

Project consits of supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor for extension of ward 125 for cardiology department

 
Gallery Image
Contractors
M/s. Rescare Medysis I PVT. Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

– Office furniture and miscellaneous works.

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Emerson make 40 KVA UPS system installed at Goa Medical College for three years

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of audio system for Autopsy Auditorium in the Forensic Block at Goa Medical College, Bambolim-Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.