Project Duration
Stipulated Date of Commencement
April 10 2023
Stipulated Date of Completion /
Likely Date of Completion September 09 2023
Likely Date of Completion September 09 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,569,144.00
Awarded for
₹ 2,818,486.97
Project highlights
Carpentary works & Modular Furniture for NICU Ward.
Contractors
M/s. Virender Kumar & Co.
Consultants
M/s. FP Project Management
See Similar Projects
Major maintenance works at Goa Medical College and Hospital at Bambolim, Goa – SH – Maintenance of landscaping works.
View Project
S.H. Carriage of Water for 3 years
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Surgical Instruments