Project Duration
Stipulated Date of Commencement
April 10 2023
Stipulated Date of Completion /
Likely Date of Completion September 09 2023
Likely Date of Completion September 09 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,569,144.00
Awarded for
₹ 2,818,486.97
Project highlights
Carpentary works & Modular Furniture for NICU Ward.
Contractors
M/s. Virender Kumar & Co.
Consultants
M/s. FP Project Management
See Similar Projects
Furniture works
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa
View Project
Electrical work.
View Project