Project Duration
Stipulated Date of Commencement
June 22 2021
Stipulated Date of Completion /
Likely Date of Completion June 30 2022
Likely Date of Completion June 30 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 32,467,692.26
Awarded for
₹ 29,549,827.65
Project highlights
The project involves upgradation of new NICU ward above ward 123 at GMC, which provides high dependency area , ventilator room, isolation room, mini OT, Preparation room etc.
Contractors
M/s. Virender Kumar & Co.,
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.
Sub Works
This project involved 1 sub works. The details of the same available below
1
Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.
0% completed
Project Duration
Stipulated Date of Commencement
June 19 2024
Stipulated Date of Completion /
Likely Date of Completion September 18 2024
Likely Date of Completion September 18 2024
Status
0%
Completed
Cost (₹)
Estimated at
₹ 4,317,391.53
Awarded for
₹ 4,520,748.60
Project highlights
Supply, Installation, Testing and Commissioning of DG Set.
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. FP Project Management
See Similar Projects
Channel Drainage Works
View Project
Upgradation and extension of existing Cottage Hospital at Chicalim, Goa – (120 Bedded Cottage Hospital, Chicalim) Civil, Plumbing, Electrical, Firefighting, HVAC, Lifts and Land development works
View Project
Procurement of hospital furniture for new ward of plastic surgery at Goa Medical College & Hospital, Bambolim, Goa.