Project Duration
Stipulated Date of Commencement
November 10 2010
Stipulated Date of Completion /
Likely Date of Completion January 08 2011
Likely Date of Completion January 08 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,712,013.00
Awarded for
₹ 6,130,371.50
Project highlights
The work includes furniture work in wards, waiting lounge, administration offices, Doctors’ room, nurses room, ceiling, signages, curtains etc.
Contractors
M/s. Mohan’s Wood Work
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.