Project Duration
Stipulated Date of Commencement
September 18 2013
Stipulated Date of Completion /
Likely Date of Completion November 17 2013
Likely Date of Completion November 17 2013
Status
100%
Completed
Cost (₹)
Awarded for
₹ 5,500,000.00
Project highlights
SITC of UPS systems at GMC
Contractors
M/s. Accutech Power Solutions Pvt. Ltd.
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.