Project Duration
Stipulated Date of Commencement
November 18 2016
Stipulated Date of Completion /
Likely Date of Completion January 17 2017
Likely Date of Completion January 17 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,424,922.50
Awarded for
₹ 1,612,747.50
Project highlights
Supply, Installation, Testing and Commissioning of Portable O.T. Light with high performance LED lights for the new burns ward at GMC
Contractors
M/s. Medex India Pvt. Ltd.
Consultants
In-house (GSIDC)