Project Duration
Stipulated Date of Commencement
January 19 2014
Stipulated Date of Completion /
Likely Date of Completion February 19 2014
Likely Date of Completion February 19 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 650,000.00
Awarded for
₹ 439,425.00
Contractors
M/S. MEDEX INDIA (P) LTD
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.