Project Duration
Stipulated Date of Commencement
January 03 2014
Stipulated Date of Completion /
Likely Date of Completion March 03 2014
Likely Date of Completion March 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 102,900.00
Awarded for
₹ 108,000.00
Contractors
M/s. B L Lifesciences Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.