Project Duration
Stipulated Date of Commencement
November 17 2013
Stipulated Date of Completion /
Likely Date of Completion January 15 2014
Likely Date of Completion January 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,963,150.00
Awarded for
₹ 2,180,968.00
Contractors
M/S. T. S. MISTRY
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Steel Operation Theatre.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa