Project Duration
Stipulated Date of Commencement
November 17 2013
Stipulated Date of Completion /
Likely Date of Completion January 15 2014
Likely Date of Completion January 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,963,150.00
Awarded for
₹ 2,180,968.00
Contractors
M/S. T. S. MISTRY
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.