Project Duration
Stipulated Date of Commencement
May 22 2015
Stipulated Date of Completion /
Likely Date of Completion May 07 2015
Likely Date of Completion May 07 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,386,310.00
Awarded for
₹ 10,777,777.00
Contractors
M/s. Harshada Trading Company
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Major maintenance works at Goa Medical College and Hospital at Bambolim, Goa – SH – Maintenance of landscaping works.
View Project
Additional infrastructure works for GMC & H – Demolition & construction of Hospital and Hostel at Mandur, Goa – S.H. – Furniture and interior works
View Project
Medical gas & vacuum plant.
View Project