Project Duration
Stipulated Date of Commencement September 29 2013
Stipulated Date of Completion /
Likely Date of Completion
March 28 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 145,763,468.00
Awarded for ₹ 158,936,223.00

Project highlights

• Total built-up area = 3610.63 sq. m.
• Ground Floor : Admin office, staff, etc.
• First Floor : 2 lecture halls.
• Second Floor : 1 lecture hall.
• Other facilities such as lift, fire fighting, HVAC, seat & desk with
self opening & closing system.

 
Gallery Image
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Furniture and Acoustical work.

100% completed
 
Project Duration
Stipulated Date of Commencement May 22 2015
Stipulated Date of Completion /
Likely Date of Completion
May 07 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,386,310.00
Awarded for ₹ 10,777,777.00
 
Contractors
Contractors
M/s. Harshada Trading Company
Consultants
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Similar Projects

See Similar Projects

Similar Project

Extension of R.M.O’s Hostel at Goa Medical College and Hospital, Bambolim Goa – Civil, Plumbing, Lifts, Electrical and Fire-Fighting Works

View Project
Similar Project

Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes, Nursing Hostel and College and Directorate of Food & Drugs.

View Project
Similar Project

Air Conditioning and Ventilation System

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.