Project Duration
Stipulated Date of Commencement
August 31 2013
Stipulated Date of Completion /
Likely Date of Completion October 30 2013
Likely Date of Completion October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,707,183.00
Awarded for
₹ 1,770,500.00
Contractors
M/s. Mediconz International
Consultants
In-house (GSIDC)
See Similar Projects
Renovation/Maintenance Of Hospitals, CHCs, PHCs, RMDs Under Directorate Of Health Services In North Goa – S.H.- Renovation/ Maintenance work of Community Health Centre at Sankhali – Comprehensive Annual Maintenance Contract of HVAC System (Chiller & AHU) for 3 Years
View Project
Full Renovation & Part Construction of the Old Heritage Building of Asilo Hospital for State Health Training Institute at Mapusa.(State Institute of Health and Family Welfare and College of Physiotherapy at restored Old Asilo Hospital, Mapusa).
View Project
Landscaping work
View Project