Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion May 20 2013
Likely Date of Completion May 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,179,000.00
Awarded for
₹ 14,022,617.80
Contractors
M/s. Concept Creators
Consultants
M/s. Effective Architectural Services