Project Duration
Stipulated Date of Commencement
December 28 2010
Stipulated Date of Completion /
Likely Date of Completion September 27 2011
Likely Date of Completion September 27 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,04,70,991.00
Awarded for
₹ 9,545,205.95
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa- SH-Supply, Installation, Testing and Commissioning of Operation Table
View Project
S.H. Carriage of Water
View Project
Supply, Installation, Testing and Commissioning of computer network with hardware and software.
View Project