Project Duration
Stipulated Date of Commencement
December 28 2010
Stipulated Date of Completion /
Likely Date of Completion September 27 2011
Likely Date of Completion September 27 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,04,70,991.00
Awarded for
₹ 9,545,205.95
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services