Project Duration
Stipulated Date of Commencement
June 16 2006
Stipulated Date of Completion /
Likely Date of Completion April 15 2007
Likely Date of Completion April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,331,777.00
Awarded for
₹ 43,374,376.00
Project highlights
Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.
Contractors
M/s. ABB Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd