Project Duration
Stipulated Date of Commencement September 14 2018
Stipulated Date of Completion /
Likely Date of Completion
November 13 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 775,410.00
Awarded for ₹ 719,999.00

Project highlights

SITC of 11KV 4 Way outdoor type RMU and other allied works at R.M.O Hostel at Goa Medical College.

 
Gallery Image
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply Installation Testing & Commissioning of Bio Medical Equipment ( Part I ) Mobile X-Ray, C-Arm, CR-System.

View Project
Similar Project

SITC of medical gas supply system (MGSS)

View Project
Similar Project

Medical gases & vacuum plant.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.