Project Duration
Stipulated Date of Commencement September 14 2018
Stipulated Date of Completion /
Likely Date of Completion
November 13 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 775,410.00
Awarded for ₹ 719,999.00

Project highlights

SITC of 11KV 4 Way outdoor type RMU and other allied works at R.M.O Hostel at Goa Medical College.

 
Gallery Image
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Primary Health Centre at Navelim, Margao, Goa.

View Project
Similar Project

Construction of IInd phase at Goa Dental College and Hospital at Bambolilm, Goa -Civil,Plumbing, internal electrical and fire fighting works-

View Project
Similar Project

Upgradation and Extension of Existing Cottage Hospital at Chicalim, Goa – Supply and Installation of Oxygen Jumbo cylinders for gas manifold.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.