Project Duration
Stipulated Date of Commencement December 15 2006
Stipulated Date of Completion /
Likely Date of Completion
September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 36,821,547.83
Awarded for ₹ 44,928,213.47

Project highlights

Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to landscape design.

 
Gallery Image
Contractors
M/s. My Associates
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Purchase of medical machinery & equipment for Upgraded 100 bedded ESI hospital at Margao -sh Supply, installation, testing and commissioning of Radiology & Imaging rquipment (2nd call)

View Project
Similar Project

Road works (concrete and paver) and landscaping works

View Project
Similar Project

False Ceiling, Acoustical Paneling and Miscellaneous Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.