Project Duration
Stipulated Date of Commencement
December 15 2006
Stipulated Date of Completion /
Likely Date of Completion September 14 2007
Likely Date of Completion September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,821,547.83
Awarded for
₹ 44,928,213.47
Project highlights
Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to landscape design.
Contractors
M/s. My Associates
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
View Project
Supply Installation testing commissioning of AC system for New Library Bldg, GMC Complex, Bambolim, Goa.
View Project
Supply, Installation and Testing and Commissioning of Patient Warming System
View Project