Project Duration
Stipulated Date of Commencement
March 04 2006
Stipulated Date of Completion /
Likely Date of Completion July 03 2006
Likely Date of Completion July 03 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,514,069.00
Awarded for
₹ 17,399,153.00
Contractors
M/s. Superb Interiors, M/s. Superb Interiors
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd