Project Duration
Stipulated Date of Commencement
July 15 2004
Stipulated Date of Completion /
Likely Date of Completion January 14 2006
Likely Date of Completion January 14 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 140,325,985.00
Awarded for
₹ 147,280,036.00
Contractors
M/s. Nagarjuna Construction Company Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 3 sub works. The details of the same available below
1
Supply, Installation, Testing and Commissioning of Medical Gas Pipelines.
100% completed
Project Duration
Stipulated Date of Commencement
October 26 2006
Stipulated Date of Completion /
Likely Date of Completion February 25 2007
Likely Date of Completion February 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,119,623.00
Awarded for
₹ 11,376,000.00
Contractors
M/s. BOC India Limited
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
Furniture and miscellaneous work.
100% completed
Project Duration
Stipulated Date of Commencement
January 05 2007
Stipulated Date of Completion /
Likely Date of Completion May 04 2007
Likely Date of Completion May 04 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,264,548.25
Awarded for
₹ 22,590,380.00
Contractors
M/s. Concept Creators
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
3
Hospital furniture work.
100% completed
Project Duration
Stipulated Date of Commencement
June 27 2008
Stipulated Date of Completion /
Likely Date of Completion September 26 2008
Likely Date of Completion September 26 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,370,852.00
Awarded for
₹ 15,401,378.00
Contractors
M/s. Royal Safe Company
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd