Project Duration
Stipulated Date of Commencement
November 24 2016
Stipulated Date of Completion /
Likely Date of Completion November 23 2017
Likely Date of Completion November 23 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,967,188.00
Awarded for
₹ 21,657,524.60
Project highlights
Maintenance works of Goa Dental college
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College S.H.:Supply, Installation, Testing and Commissioning of Audio Power Amplifiers for Lecture Halls 4, 5 & 6 at Goa Medical College