Project Duration
Stipulated Date of Commencement
July 05 2015
Stipulated Date of Completion /
Likely Date of Completion August 31 2022
Likely Date of Completion August 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,790,585.00
Awarded for
₹ 9,596,000.00
Project highlights
Supplying Lifts for dental phase II building
Contractors
M/s. OTIS Elevator Company (India) Ltd.
Consultants
M/s. FP Project Management
See Similar Projects
Interior work
View Project
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.
View Project
Operation and maintenance of centralized air conditioning plant of Goa Medical College & Hospital – Replacement of AHUs.
View Project